Checks
After installing and connecting the SAM4 components it is time to check the installation. Let's start with the general set-up check.
General checks
Check whether all cables have been correctly connected.
Check whether the current sensors have been installed around the correct phase wires.
Check whether the current sensors have been installed in the correct direction around the phase wires.
Check whether the voltage branches are installed on the correct phase wire.
Check whether the wires of the voltage branches are connected to the correct connector on the DAQ.
If you use feed-through terminal blocks, check whether the phase wires have been connected correctly into the fused terminal blocks and whether the fuse has been installed and is intact.
Check whether the phase wires of the electric motor have been correctly connected to the VFD.
Switch on the power. All equipment will be switched on. Check whether all components are operating correctly.
Notice If you want to optimize the antenna position, follow the instructions from the SAM4 setup tool.